Rest of the 1st deck planking is mostly made of veneer sheets, such as these:

 

post-19661-0-13135500-1468268405_thumb.jpg

 

Dry fit looks like this:

 

post-19661-0-93818000-1468268441_thumb.jpg

 

Parts 162 and 163 require small support pieces on either end cut from planking strips:

 

post-19661-0-02437300-1468268500_thumb.jpg

Current :

HMS Sphinx by Vanguard

-------------

Completed:

Orient Express Sleeping Car by Amati

Bluenose II (Artesania Latina)

Istanbul Tram - Occre

Bluenose II - Artesania Latina

Bosphorus Sandal Fishing Boat

Riva Aquarama - Amati

Titanic - Mantua

Bosphorus Fishing Boat - Tersane Model

San Juan Nepomuceno - Artesania Latina

Bluenose - Billing Boats

Link to comment
Share on other sites

Dry fitting revealed that the thin "tail" at the back seems to require more critical positioning:

 

post-19661-0-93081300-1468268642_thumb.jpg

 

Some edges overlap slightly. I'll have to trim them a bit (better leave some gap instead of overlap, since this is only the first planking):

 

post-19661-0-59788600-1468268696_thumb.jpg

 

Parts 168 and 169. The parts 14C and 14D will be supporting them:

 

post-19661-0-56849800-1468268776_thumb.jpg

 

Current :

HMS Sphinx by Vanguard

-------------

Completed:

Orient Express Sleeping Car by Amati

Bluenose II (Artesania Latina)

Istanbul Tram - Occre

Bluenose II - Artesania Latina

Bosphorus Sandal Fishing Boat

Riva Aquarama - Amati

Titanic - Mantua

Bosphorus Fishing Boat - Tersane Model

San Juan Nepomuceno - Artesania Latina

Bluenose - Billing Boats

Link to comment
Share on other sites

Here I noticed a problem. Check the following 2 photos where I show the "removable" section. In the first photo it is out of its slot and in the second photo it is in place.

 

Photo 1:

post-19661-0-33511100-1468268947_thumb.jpg

 

Photo 2:

post-19661-0-56208900-1468268954_thumb.jpg

 

Parts 168 and 169 are supposed to cover the open area on the left and right side of this removable part while parts 14C and 14D are to be glued on either sides to support them. However if you make the mistake of gluing the parts 14C and 14D (like I did - just look at the glue stains), there is no way to place the removable part anymore. Check from this photo how it would have blocked the removable section from placing to its slot:

 

post-19661-0-83825500-1468269234_thumb.jpg

 

So I had to cut them short enough so that they won't block the removable section but still support the parts 168 and 169:

 

post-19661-0-51872700-1468269350_thumb.jpg

 

 

Current :

HMS Sphinx by Vanguard

-------------

Completed:

Orient Express Sleeping Car by Amati

Bluenose II (Artesania Latina)

Istanbul Tram - Occre

Bluenose II - Artesania Latina

Bosphorus Sandal Fishing Boat

Riva Aquarama - Amati

Titanic - Mantua

Bosphorus Fishing Boat - Tersane Model

San Juan Nepomuceno - Artesania Latina

Bluenose - Billing Boats

Link to comment
Share on other sites

But before gluing, these two parts have to be curved a little in order to fit nicely:

 

post-19661-0-23721200-1468269466_thumb.jpg

 

post-19661-0-75428000-1468269468_thumb.jpg

 

post-19661-0-33243900-1468269471_thumb.jpg

Current :

HMS Sphinx by Vanguard

-------------

Completed:

Orient Express Sleeping Car by Amati

Bluenose II (Artesania Latina)

Istanbul Tram - Occre

Bluenose II - Artesania Latina

Bosphorus Sandal Fishing Boat

Riva Aquarama - Amati

Titanic - Mantua

Bosphorus Fishing Boat - Tersane Model

San Juan Nepomuceno - Artesania Latina

Bluenose - Billing Boats

Link to comment
Share on other sites

The side pieces for some reason extend to outside a little bit. This also shows in the instructions. They will probably be trimmed later, since in the instruction manual the later pages show so.

 

post-19661-0-88821700-1468269612_thumb.jpg

 

post-19661-0-29530100-1468269615_thumb.jpg

 

post-19661-0-99419300-1468269616.jpg

Current :

HMS Sphinx by Vanguard

-------------

Completed:

Orient Express Sleeping Car by Amati

Bluenose II (Artesania Latina)

Istanbul Tram - Occre

Bluenose II - Artesania Latina

Bosphorus Sandal Fishing Boat

Riva Aquarama - Amati

Titanic - Mantua

Bosphorus Fishing Boat - Tersane Model

San Juan Nepomuceno - Artesania Latina

Bluenose - Billing Boats

Link to comment
Share on other sites

A sneak peek to the current status:

 

post-19661-0-74339500-1468269686_thumb.jpg

Current :

HMS Sphinx by Vanguard

-------------

Completed:

Orient Express Sleeping Car by Amati

Bluenose II (Artesania Latina)

Istanbul Tram - Occre

Bluenose II - Artesania Latina

Bosphorus Sandal Fishing Boat

Riva Aquarama - Amati

Titanic - Mantua

Bosphorus Fishing Boat - Tersane Model

San Juan Nepomuceno - Artesania Latina

Bluenose - Billing Boats

Link to comment
Share on other sites

Planking the "removable section"

 

post-19661-0-48234600-1468269750.jpg

 

post-19661-0-90161200-1468269752_thumb.jpg

Current :

HMS Sphinx by Vanguard

-------------

Completed:

Orient Express Sleeping Car by Amati

Bluenose II (Artesania Latina)

Istanbul Tram - Occre

Bluenose II - Artesania Latina

Bosphorus Sandal Fishing Boat

Riva Aquarama - Amati

Titanic - Mantua

Bosphorus Fishing Boat - Tersane Model

San Juan Nepomuceno - Artesania Latina

Bluenose - Billing Boats

Link to comment
Share on other sites

Coverings at the stern. The instructions call for trimming the ends of the thick mahogany arcs with a file to fit the flow of the stern (note the file symbols on the instructions). This sounds virtually unpractical to me since the piece is really thick and there is quite a lot to get rid of. Hence, I used a combination of saw, file, sandpaper, and knife to get the desired result:

 

post-19661-0-22434300-1468270051_thumb.jpg

 

post-19661-0-98654200-1468270052.jpg

 

Bending the veneer parts on the lower part to fit easily:

 

post-19661-0-43270100-1468270055_thumb.jpg

 

Veneers in place:

 

post-19661-0-68785900-1468270057_thumb.jpg

 

This is why the mahogany arcs need trimming:

 

post-19661-0-19348100-1468270060_thumb.jpg

 

Trimmed:

 

post-19661-0-08401200-1468270066_thumb.jpg

 

And dry fitted to place:

 

post-19661-0-87189100-1468270067_thumb.jpg

 

post-19661-0-27348400-1468270069_thumb.jpg

 

Edited by aydingocer

Current :

HMS Sphinx by Vanguard

-------------

Completed:

Orient Express Sleeping Car by Amati

Bluenose II (Artesania Latina)

Istanbul Tram - Occre

Bluenose II - Artesania Latina

Bosphorus Sandal Fishing Boat

Riva Aquarama - Amati

Titanic - Mantua

Bosphorus Fishing Boat - Tersane Model

San Juan Nepomuceno - Artesania Latina

Bluenose - Billing Boats

Link to comment
Share on other sites

END of BUILD DAY 17.

 

4 hours today.

 

59 hours into build in total.

 

Time is up for today. I will glue the mahogany pieces tomorrow.

Thanks for watching.

Edited by aydingocer

Current :

HMS Sphinx by Vanguard

-------------

Completed:

Orient Express Sleeping Car by Amati

Bluenose II (Artesania Latina)

Istanbul Tram - Occre

Bluenose II - Artesania Latina

Bosphorus Sandal Fishing Boat

Riva Aquarama - Amati

Titanic - Mantua

Bosphorus Fishing Boat - Tersane Model

San Juan Nepomuceno - Artesania Latina

Bluenose - Billing Boats

Link to comment
Share on other sites

Aydin,

 

Why didn't you glue 14C and 14D to the removable part ... or at least the part from them which is above the removable part. You'll be lacking support if I'm not mistaken ...

Carl

"Desperate affairs require desperate measures." Lord Nelson
Search and you might find a log ...

 

Link to comment
Share on other sites

Aydin,

 

Why didn't you glue 14C and 14D to the removable part ... or at least the part from them which is above the removable part. You'll be lacking support if I'm not mistaken ...

 

Hi Carl,

 

14C and 14D are meant to support parts 168 and 169 with glue. These parts are fixed. According to the instructions, the removable part (actually it is the engine lid) is positioned between them.

 

In the photo below, you can see 168 and 169 on the sides and the lid (which now includes 170 and 171) in the middle:

 

post-19661-0-41567900-1468322940_thumb.jpg

 

This is the view when the lid is removed (here note that the lid is sitting on the 2 wooden "hooks" inside). The red drawing on the left indicates where the 14C would have occupied if it had been installed as in the instructions (same on the other side). But in that case it is impossible to place the lid anymore.

 

post-19661-0-12391000-1468322985_thumb.jpg

 

post-19661-0-50608100-1468323121_thumb.jpg

 

See also the red lines I have drawn on the instructions:

 

post-19661-0-36978500-1468323169_thumb.jpg

 

So my solution was to chop off 14C and 14D short enough to stop preventing the lid and long enough to support the side pieces.

 

:)

Current :

HMS Sphinx by Vanguard

-------------

Completed:

Orient Express Sleeping Car by Amati

Bluenose II (Artesania Latina)

Istanbul Tram - Occre

Bluenose II - Artesania Latina

Bosphorus Sandal Fishing Boat

Riva Aquarama - Amati

Titanic - Mantua

Bosphorus Fishing Boat - Tersane Model

San Juan Nepomuceno - Artesania Latina

Bluenose - Billing Boats

Link to comment
Share on other sites

Hi Aydin.

She is coming along very nicely.

Problems lead to solutions and knowledge. In saying that you must have learnt a lot by building this kit :)

Nice work through the the build.

 

Regards Antony.

Best advice ever given to me."If you don't know ..Just ask.

Completed Mayflower

Completed Fun build Tail boat Tailboat

Completed Build Chinese Junk Chinese Pirate Junk

Completed scratch built Korean Turtle ship 1/32 Turtle ship

Completed Santa Lucia Sicilian Cargo Boat 1/30 scale Santa Lucia

On hold. Bounty Occre 1/45

Completed HMS Victory by DeAgostini modelspace. DeAgostini Victory Cross Section

Completed H.M.S. Victory X section by Coral. HMS Victory cross section

Completed The Black Pearl fun build Black Queen

Completed A large scale Victory cross section 1/36 Victory Cross Section

Link to comment
Share on other sites

Yep, I agree Antony and Carl. This is one of the main purposes of sharing your build in a forum: Deliver your experience to the other builders as someone who has been there.

Current :

HMS Sphinx by Vanguard

-------------

Completed:

Orient Express Sleeping Car by Amati

Bluenose II (Artesania Latina)

Istanbul Tram - Occre

Bluenose II - Artesania Latina

Bosphorus Sandal Fishing Boat

Riva Aquarama - Amati

Titanic - Mantua

Bosphorus Fishing Boat - Tersane Model

San Juan Nepomuceno - Artesania Latina

Bluenose - Billing Boats

Link to comment
Share on other sites

BUILD DAY 18. STERN 1st PLANKING.

 

Today I had some 1,5 hours which I could use for 1st planking the stern. But before that I glued 2 small support pieces:

 

post-19661-0-46987800-1468418116_thumb.jpg

 

post-19661-0-41307600-1468418119_thumb.jpg

Edited by aydingocer

Current :

HMS Sphinx by Vanguard

-------------

Completed:

Orient Express Sleeping Car by Amati

Bluenose II (Artesania Latina)

Istanbul Tram - Occre

Bluenose II - Artesania Latina

Bosphorus Sandal Fishing Boat

Riva Aquarama - Amati

Titanic - Mantua

Bosphorus Fishing Boat - Tersane Model

San Juan Nepomuceno - Artesania Latina

Bluenose - Billing Boats

Link to comment
Share on other sites

Glued the thick curvy mahogany frame which I had filed ready yesterday. They are now covering around the stern. 

 

Apparently stern planking should be done in such a way that the 1st planking (which I am doing now using 1,5x7mm lime as the previous plankings) shall be level with the veneer parts on the bottom ( i.e. parts 172 and 173), while leaving some offset with the mahogany frames, so that they will be level with the 2nd planking (which will be done using 1,5x8mm mahogany strips). So I glue them around 1,5mm offset (see the photo):

 

post-19661-0-35615400-1468418524_thumb.jpg

Current :

HMS Sphinx by Vanguard

-------------

Completed:

Orient Express Sleeping Car by Amati

Bluenose II (Artesania Latina)

Istanbul Tram - Occre

Bluenose II - Artesania Latina

Bosphorus Sandal Fishing Boat

Riva Aquarama - Amati

Titanic - Mantua

Bosphorus Fishing Boat - Tersane Model

San Juan Nepomuceno - Artesania Latina

Bluenose - Billing Boats

Link to comment
Share on other sites

This is how much you'll have to bend the stern planks on the average. I did not have to soak them, my plank bender was good enough to handle it:

 

post-19661-0-33951500-1468418749_thumb.jpg

 

Current :

HMS Sphinx by Vanguard

-------------

Completed:

Orient Express Sleeping Car by Amati

Bluenose II (Artesania Latina)

Istanbul Tram - Occre

Bluenose II - Artesania Latina

Bosphorus Sandal Fishing Boat

Riva Aquarama - Amati

Titanic - Mantua

Bosphorus Fishing Boat - Tersane Model

San Juan Nepomuceno - Artesania Latina

Bluenose - Billing Boats

Link to comment
Share on other sites

Stern 1st planking ready:

 

post-19661-0-66593800-1468418801_thumb.jpg

Current :

HMS Sphinx by Vanguard

-------------

Completed:

Orient Express Sleeping Car by Amati

Bluenose II (Artesania Latina)

Istanbul Tram - Occre

Bluenose II - Artesania Latina

Bosphorus Sandal Fishing Boat

Riva Aquarama - Amati

Titanic - Mantua

Bosphorus Fishing Boat - Tersane Model

San Juan Nepomuceno - Artesania Latina

Bluenose - Billing Boats

Link to comment
Share on other sites

END of BUILD DAY 18.

 

1,5 hours today.

60,5 hours into build in total.
 
This is the status at the end of day. Thanks for watching.
 
post-19661-0-33198000-1468418917_thumb.jpg

Current :

HMS Sphinx by Vanguard

-------------

Completed:

Orient Express Sleeping Car by Amati

Bluenose II (Artesania Latina)

Istanbul Tram - Occre

Bluenose II - Artesania Latina

Bosphorus Sandal Fishing Boat

Riva Aquarama - Amati

Titanic - Mantua

Bosphorus Fishing Boat - Tersane Model

San Juan Nepomuceno - Artesania Latina

Bluenose - Billing Boats

Link to comment
Share on other sites

BUILD DAY 19. COMPLETING 1st PLANKING.

 

  :D No, I am not one of those who have been hypnotised by Pokemon Go, which became available in Finland as of yesterday!  :D

 

I have had roughly 4 hours today to finally complete 1st planking and start preparing the hull for the second planking. 

 

First, finishing the first planking of the removable engine cover (1st planking of this section is made by veneer sheets). After the planks are glued, the section should fit in its space nicely. Some parts in the stern prevented it. I had to use a rasp at the stern to get rid of those obstacles. Here are a few details:

 

Positioning of planks (parts 175, 76, 177) require some attention. The first photo below is a demonstration of wrong positioning, even though it looks tempting:

 

post-19661-0-74210900-1468781103_thumb.jpg

 

This is the right way:

 

post-19661-0-67555100-1468781132_thumb.jpg

 

If you look carefully at where the middle part sits, you will notice that I glued thin strips, which will raise the middle piece about a millimetre or so. Without them, the middle piece was touching the stern. so that was the reason. 

 

The middle part in place, all glued:

 

post-19661-0-26331600-1468781155_thumb.jpg

 

Lid in place:

 

post-19661-0-91698000-1468781177_thumb.jpg

Edited by aydingocer

Current :

HMS Sphinx by Vanguard

-------------

Completed:

Orient Express Sleeping Car by Amati

Bluenose II (Artesania Latina)

Istanbul Tram - Occre

Bluenose II - Artesania Latina

Bosphorus Sandal Fishing Boat

Riva Aquarama - Amati

Titanic - Mantua

Bosphorus Fishing Boat - Tersane Model

San Juan Nepomuceno - Artesania Latina

Bluenose - Billing Boats

Link to comment
Share on other sites

Next in line is to fill the gaps. I use this furniture grade water based wood filler which I found in a local hardware store. It is quite smooth and  according to the specs it dries in 1 hour per mm thickness:

 

post-19661-0-69784600-1468781715_thumb.jpg

 

 

 

 

Current :

HMS Sphinx by Vanguard

-------------

Completed:

Orient Express Sleeping Car by Amati

Bluenose II (Artesania Latina)

Istanbul Tram - Occre

Bluenose II - Artesania Latina

Bosphorus Sandal Fishing Boat

Riva Aquarama - Amati

Titanic - Mantua

Bosphorus Fishing Boat - Tersane Model

San Juan Nepomuceno - Artesania Latina

Bluenose - Billing Boats

Link to comment
Share on other sites

Gaps filled with help of a spatula. Now a lunch break (until it dries):

 

post-19661-0-17749700-1468781798_thumb.jpg

 

 

 

 

Current :

HMS Sphinx by Vanguard

-------------

Completed:

Orient Express Sleeping Car by Amati

Bluenose II (Artesania Latina)

Istanbul Tram - Occre

Bluenose II - Artesania Latina

Bosphorus Sandal Fishing Boat

Riva Aquarama - Amati

Titanic - Mantua

Bosphorus Fishing Boat - Tersane Model

San Juan Nepomuceno - Artesania Latina

Bluenose - Billing Boats

Link to comment
Share on other sites

Back to work. Before sanding I decided to use some scraper in order to get rid of the glue residues and to level the stripes for helping the sanding process. I have this set of scrapers with different contours quite useful for this boat, which has rather curvy surface:

 

post-19661-0-28605700-1468782096_thumb.jpg

 

They work quite effectively indeed:

 

post-19661-0-74835000-1468782128_thumb.jpg

 

post-19661-0-05076900-1468782131_thumb.jpg

Edited by aydingocer

Current :

HMS Sphinx by Vanguard

-------------

Completed:

Orient Express Sleeping Car by Amati

Bluenose II (Artesania Latina)

Istanbul Tram - Occre

Bluenose II - Artesania Latina

Bosphorus Sandal Fishing Boat

Riva Aquarama - Amati

Titanic - Mantua

Bosphorus Fishing Boat - Tersane Model

San Juan Nepomuceno - Artesania Latina

Bluenose - Billing Boats

Link to comment
Share on other sites

END of BUILD DAY 19.

 

4 hours today.

64,5 hours into build in total.
 
Scraping is complete now and  the boat is ready for sanding. This is the status at the end of day. Thanks for watching.
 
post-19661-0-99262400-1468782433_thumb.jpg
 
post-19661-0-18470300-1468782436_thumb.jpg
 
post-19661-0-59686200-1468782437_thumb.jpg

Current :

HMS Sphinx by Vanguard

-------------

Completed:

Orient Express Sleeping Car by Amati

Bluenose II (Artesania Latina)

Istanbul Tram - Occre

Bluenose II - Artesania Latina

Bosphorus Sandal Fishing Boat

Riva Aquarama - Amati

Titanic - Mantua

Bosphorus Fishing Boat - Tersane Model

San Juan Nepomuceno - Artesania Latina

Bluenose - Billing Boats

Link to comment
Share on other sites

Aydin,

That looks so great, looking forward to next part of the build.

 

Please, visit our Facebook page!

 

Respectfully

 

Per aka Dr. Per@Therapy for Shipaholics 
593661798_Keepitreal-small.jpg.f8a2526a43b30479d4c1ffcf8b37175a.jpg

Finished: T37, BB Marie Jeanne - located on a shelf in Sweden, 18th Century Longboat, Winchelsea Capstan

Current: America by Constructo, Solö Ruff, USS Syren by MS, Bluenose by MS

Viking funeral: Harley almost a Harvey

Nautical Research Guild Member - 'Taint a hobby if you gotta hurry

Link to comment
Share on other sites

Hi Aydin.

WOW. Nice very nice.

Ideal boat to use the scrappers on. Nice flowing area's

The lines on the boat are really showing up now. Only a Italion could design lines like that :)

 

Regards Antony.

Best advice ever given to me."If you don't know ..Just ask.

Completed Mayflower

Completed Fun build Tail boat Tailboat

Completed Build Chinese Junk Chinese Pirate Junk

Completed scratch built Korean Turtle ship 1/32 Turtle ship

Completed Santa Lucia Sicilian Cargo Boat 1/30 scale Santa Lucia

On hold. Bounty Occre 1/45

Completed HMS Victory by DeAgostini modelspace. DeAgostini Victory Cross Section

Completed H.M.S. Victory X section by Coral. HMS Victory cross section

Completed The Black Pearl fun build Black Queen

Completed A large scale Victory cross section 1/36 Victory Cross Section

Link to comment
Share on other sites

BUILD DAY 20. 2nd PLANKING COMMENCES.

 

Today I spent some 1-2 hours for sanding, after which I concluded that the surface is smooth enough for 2nd planking. My tools were Proxxon orbital sander with 180 grit paper and a sanding drum, same grit paper,  self-made sanding drum from a pool toy (water gun). The latter has been a perfect tool with its soft cushion especially on the curvy surfaces:

 

post-19661-0-42045200-1468870270.jpg

 

The hull is now ready for 2nd planking:

 

post-19661-0-25739600-1468870272_thumb.jpg

Current :

HMS Sphinx by Vanguard

-------------

Completed:

Orient Express Sleeping Car by Amati

Bluenose II (Artesania Latina)

Istanbul Tram - Occre

Bluenose II - Artesania Latina

Bosphorus Sandal Fishing Boat

Riva Aquarama - Amati

Titanic - Mantua

Bosphorus Fishing Boat - Tersane Model

San Juan Nepomuceno - Artesania Latina

Bluenose - Billing Boats

Link to comment
Share on other sites

Let the 2nd planing begin! 

 

Planking material: 1,5mm x 8mm mahogany (as opposed to 1,5mm x 7mm lime used in first planking). This is interesting as I would normally expect the 2nd planking strips to be thinner. These ones are as thick as the lime planks underneath.

 

2nd planking follows pretty much the same sequence as the first planking. Start with 1 strip from the center of the each side of the hull, then switch to the middle of the bottom, then continue in alternating turns. 

 

post-19661-0-71178100-1468870611_thumb.jpg

Current :

HMS Sphinx by Vanguard

-------------

Completed:

Orient Express Sleeping Car by Amati

Bluenose II (Artesania Latina)

Istanbul Tram - Occre

Bluenose II - Artesania Latina

Bosphorus Sandal Fishing Boat

Riva Aquarama - Amati

Titanic - Mantua

Bosphorus Fishing Boat - Tersane Model

San Juan Nepomuceno - Artesania Latina

Bluenose - Billing Boats

Link to comment
Share on other sites

I avoid using nails for fixing on this stage, since the holes will be hard to conceal later. Instead I use masking tape (and a little bit more CA glue) to compensate.

 

post-19661-0-96821700-1468870742_thumb.jpg

 

post-19661-0-33240900-1468870745_thumb.jpg

 

Current :

HMS Sphinx by Vanguard

-------------

Completed:

Orient Express Sleeping Car by Amati

Bluenose II (Artesania Latina)

Istanbul Tram - Occre

Bluenose II - Artesania Latina

Bosphorus Sandal Fishing Boat

Riva Aquarama - Amati

Titanic - Mantua

Bosphorus Fishing Boat - Tersane Model

San Juan Nepomuceno - Artesania Latina

Bluenose - Billing Boats

Link to comment
Share on other sites

Join the conversation

You can post now and register later. If you have an account, sign in now to post with your account.

Guest
Reply to this topic...

×   Pasted as rich text.   Paste as plain text instead

  Only 75 emoji are allowed.

×   Your link has been automatically embedded.   Display as a link instead

×   Your previous content has been restored.   Clear editor

×   You cannot paste images directly. Upload or insert images from URL.

  • Recently Browsing   0 members

    • No registered users viewing this page.
×
×
  • Create New...