Jump to content

aydingocer

Members
  • Posts

    858
  • Joined

  • Last visited

Everything posted by aydingocer

  1. ENGINE, EXHAUST PIPE AND GAS TANK Exhaust pipe is fixed to handrails using a metal plate. Gas tank is in fact a canister hanging on the side (Note the copper wire resembling the gas input pipe from the canister to the engine)
  2. Build days: 20-21 Finished building. 5.5 hours in three days, 49 hours in total. I am glad to announce that my Bosphorus Fishing Boat is finally complete. Here is a log of final steps: ANCHOR Anchor consists of 3 hooks to be glued to the main rod, which is attached to a chain and finally to a thread. I had to drill the hole which the chain is hooked using a 0,5mm drill bit. And in place:
  3. Build day: 17-18-19 3 hours in three days, 43.5 hours in total. It is about time to start painting the hull, i.e. before installing the ornaments and other accessories. Overall total work did not take too long after all, only waiting in between the drying time of the paint and varnish. Below are some photos. Photo from the package. I like the choice of colors therefore I intend to make similar (remember this is a serial production boat which can come in any color so it is up to you to paint it how you like it or where you want to display it): White stripe at waterline: Varnish inside This is the status at the moment. Rudder and oars will be painted separately. Thanks for watching.
  4. Build day: 15-16 6 hours in two days, 41,5 hours in total. In these two days I worked on - the handrails, - engine ramp, - rudder, - oars - engine After these steps now the boat is ready for painting. Once the essential parts have been painted/varnished, it will be about installing the other accessories like hooks, anchor, spear etc. I am posting quite many photos below, with some explanations where I feel helps understand what's going on. Below I installed the posts for the oars (you'll notice them in both port and starboard, a bit offset the seat): Engine ramps: Floor boards getting frames: D shaped strips following the handrail on the hull: THE RUDDER Construction of rudder follows and interesting and smart way: In order to maintain correct size of the slot where the handle will be inserted, one of the support strips is glued before removing the rudder pieces from the plywood. One of the support pieces glued: The parts have now been removed from the plywood: Rudder "handle" is inserted (dry fitted at the moment since it will be on the way while drilling as well as painting): These small parts are used for attaching the rudder to the hull: OARS: Each one of the oars are made of two pieces. The longer piece which is removed from plywood needs to be tapered on the water end and and rounded on the other end, to fit the second piece. Below is a series of pics to show the progress: Sanding away the laser cut burns from the sides (photo shows the sanded piece vs not sanded): ENGINE: Engine comes in cast metal. I have to say I was quite disappointed with the quality. Inaccurate parts with lots of burrs here and there. Besides, some parts (you will see in the later photos) were impossible to glue. The rod is supposed to go through all the way through the components but there was no hole in them and there was no way I would waste my drill bits trying to drill hole through the metal. So I just glued them using CA and only drilled a 2-3mm hole to stick the rod, which will go to the propeller. The two pieces you will see in the second last photo will not fit therefore I will just leave them out... This is the status after these two days. Thank you for watching. /Aydin
  5. Build day: 14 1,5 hours today, 35,5 hours in total. Continuing with the handrails. 4 of the 2x2mm strips need to be rounded to a D shape. Two of them will be used on the outmost rails, 2 of them will be aligned approximately 1cm below the handrails, outside the, parallel to rails. Below is a rough cross-section illustration of how the rails are formed: Strips filed and sanded to D shape: Gluing the two inner rail strips: This is all for today. Next, I will glue the D shaped strips and sand all of them to level. Thanks for watching.
  6. Next in line is adding the handrails. Instead of struggling with bending a single wide strip, they will be constructed by gluing thinner strips together. It starts with 1x2mm walnut strips glued right over the topmost hull plank, following it flush. (This is the part I finished today) Next, more walnut strips (2x2mm) will be added both inside and outside of this strip. First strip being glued: First line of strips completed. This is the status after today. Thanks for watching! /Aydin
  7. Started my own version of stern deck, planking directly on the hull. If you check my earlier posts, I had prepared the deck independently off the hull as instructed, planking on the false deck supplied. However the false deck had been warped so badly in the package that it kept warping back no matter how many times I soaked it and clamped flat until dry. With a last hope I completed the planking but still it wasn't acceptable to my expectations. So now I first glued the 1x5mm strip across the 3rd rib and proceed with planking: This is the structure which I discarded: Stern deck planked:
  8. Build day: 13 4 hours today, 34 hours in total. Continuing with the "ribs" and proceeding on the stern deck. Bending the 2x2mm strips using the electric bender:
  9. Thank you very much for your reply, Robert and it is never too late for answer :). I think the waterway had been already glued in your case. How hard was it to remove the the waterway piece properly clean after you have used the blade on the marked lines? Did you use a weaker glue when you fixed it on the false deck in order to make it easy to rip off pieces afterwards? Or was it just easy to do it? /Aydin
  10. Well, I searched around and found this topic in this forum about my question above. I will check it out but any first hand experience tips are still appreciated (I tried to edit my post but Forum did not let me, therefore I had to post a new reply about it).
  11. Hi Bertu, Excellent job indeed. Congratulations. I have this kit as my next project and I was wondering how did you manage to get those plank nibs so smoothly into the waterways (see picture below for what I mean)? Did you first install the waterways and cut off parts as the planks come by, or did you use some other way? Can you share your method? BR; Aydin
  12. Build day: 12 2 hours today, 30 hours in total. Today I spent some time for installing the support bars (or ribs or whatever they are called). I used the electric hot plank bender most of the way instead of the Amati clamping plank bender in order not to make any dents, since in this case the inner side of the strips are visible (as opposed to hull planking where the outer side is visible). This process slowed down the work significantly. Here is the work so far. The boards on the floor are still dry-fitted. Thanks for watching.
  13. End of Build day: 11 2 hours today, 28 hours in total. Thanks for watching. Floor boards dry-fitted to see how they would look. You may notice that I also added the strips between the ribs on front deck. They look a bit different than in the plan but I wanted to do them this way. I also glued the middle seat. Time will tell if I plank that, too, or just lacquer nicely... time will show.
  14. Step 4: Flip the boards and sand the surface (sanding better be done at this stage, before gluing the engine box lower frames (see 2nd image): Glue the lower frames of the engine box:
  15. Step 3: Cut the binding strips (which will be on the bottom, once the board structures are flipped) and glue them: I thought it would be easier to align the boards if I start by gluing the binding strips to the middle board first:
  16. Step 2: Use template drawings to cut the boards from 10x2mm strips: Temporarily aligned to check that they are almost symmetric and identical:
  17. Build day: 11 - Floorboards I wanted to move a bit ahead and make the floorboards today. I could have continued with installing the "ribs" but I just wasn't up to do extensive strip bending work, mainly because I would have to use hot electric bender in order to avoid dents and bites. So, first step: Cut off the 1:1 scale drawing from the plan sheet and take a copy of it:
  18. Front deck top, wall, cabinet cover and ribs are in place. It will be complete once I have installed the 1x2mm strips along the edges of the deck and the wall in order to cover the gaps. End of Build day: 10 3 hours today, 26 hours in total. Thanks for watching.
  19. There is no option for me but to rip the decks off and plank straight on the bulkheads. There is no hope trying to reuse the decks. So I found suitable strips (slightly thicker to compensate for the thickness of the plywood deck guide) from my older stock and started planking right on the bulkheads. Note I used walnut planking on the front wall just for a change of taste.
×
×
  • Create New...