Jump to content

Recommended Posts

Posted

Build Log Index

Date: 15/09/2024

Time worked today: 4 hours.

Total time spent on build: 86 hours.

 

Yard and Bowsprit Manufacture Part 3

Work is still progressing slowly and steadily with making all the various yards. I have always found this aspect of the build process takes a great deal of time.

 

All work is now complete on the spritsail yard, the fore & main topsail masts, the fore & main topgallant yards, Jibboom and the main &driver booms.

 

I only have to add the PE parts, the various blocks / deadeyes and footropes to the bowsprit and fore & main lower yards which I hope will be completed in the next day or two.

 

The following photo shows all the fore & main mast yards, prior to the final painting phase, and before completion of the lower yards.

A-0341.thumb.JPG.ae8171882027044e4e50e0cf49438b50.JPG

I decided to add the planking to the hexagonal section of the main and fore lower yards as I think this look much better.

A-0342.thumb.JPG.60757ed0629684c23f7a8aa0caa2848a.JPG

The next photo shows the completed spritsail, after painting. I might have to revisit one of the outer footropes and there are not as even as I would like (yellow arrows)

A-0343.thumb.JPG.14f8b1c6edb022f9109dac266ce2e0c9.JPG

The next photo shows the completed fore and main topsail yards.

A-0344.thumb.JPG.7480b7eda9d8713f149734cc078eefd5.JPG

The final photo of this post shows fore and main topgallant yards.

A-0345.thumb.JPG.400890e56a3ad65dc843d5c95636086c.JPG

Glenn (UK)

Posted

Build Log Index

Date: 18/09/2024

Time worked today: 4 hours.

Total time spent on build: 90 hours.

 

Yard and Bowsprit Manufacture Part 4

I have now completed all the work related to making the yards and booms.

 

The first two photos show the spritsail yard which has been temporarily pinned to the bowsprit. The various deadeyes to the bowsprit will be added later today.

A-0346.thumb.JPG.1ec8c7900d958ed2137cfb4dfcf38ac9.JPGA-0347A.thumb.JPG.464571e7c6275ec4e6a6ad04e408d39f.JPG

The next two photos show the various yards and booms temporarily pinned to the main, main topsail and main topgallant masts.

A-0348.thumb.JPG.4d89986cf3607e32bcdb953bbd46614b.JPGA-0349.thumb.JPG.bdd281e4deed5916d26305dce522ee1c.JPG

The final photo show the various yards temporarily pinned to the fore, fore topsail and fore topgallant masts.

A-0350.thumb.JPG.f6778752078e467853e84e10e74b91ba.JPG

Glenn (UK)

Posted

Build Log Index

Date: 19/09/2024

Time worked today: 2 hours.

Total time spent on build: 92hours.

 

Bowsprit Installation

I have now started the rigging phase of the build. I started by adding and securing the jibboom and spritsail yard to the bowsprit. Once that was done the bowsprit assembly was added to the hull.

 

The first rigging task was to add the gammoning.

A-0351.thumb.JPG.f6db96aef27c8a58266787ba7389beb4.JPG

Next I rigged the spritsail yard lifts.

A-0352.thumb.JPG.4bf3bcf2b05650f7fb38eb9e07292dd9.JPGA-0353.thumb.JPG.25f52bb7b64e142282e803fe6480f396.JPG

The next photo shows the spritsail yard tye blocking rigging.

A-0354.thumb.JPG.58b7152cde823bf0b61d65b0b346d3de.JPG

I made sure the spritsail yard lifts and tyes rigging was fed through the bowsprit fairlead before they were belayed. The second photo shows the belaying of the spritsail tye to a belaying pin.

A-0355.thumb.JPG.9fc19432e0da24b971e482a35730a919.JPGA-0356.thumb.JPG.42425862b3b492bc41fc322c535ba5db.JPG

The final photo shows the belaying of the spritsail yard lifts.

A-0357.thumb.JPG.eb54b19ca0b34f99ccc0af59de92e16a.JPG

Glenn (UK)

Posted

Build Log Index

Date: 21/09/2024

Time worked today: 1 hour.

Total time spent on build: 93hours.

 

Hammock Cranes

I forgot to add the following photo showing the bowsprit, jibboom and spritsail yard

A-0358.thumb.JPG.e90645a4dac787385658a770de069512.JPG

I realised I had not added the hammock cranes to the hull and it is much easier to install these before I start work on the shrouds.

 

There are 16 hammock cranes installed each side. I test fitted each crane before they were glued in place. I used wood glue. Once they were all fitted I added the rigging.

A-0359.thumb.JPG.cffecf7c92afaf635b6618d63a0feb65.JPGA-0360.thumb.JPG.c3ba81ef1c6bc4bec1caf94e47352d99.JPGA-0361.thumb.JPG.a207c886cdec97dded52e5f3f4f2f171.JPGA-0362.thumb.JPG.a811d0004336abe55a3219e3a7393384.JPG

I have made the fore and main mast shroud pairs and I am now ready to start work in rigging these.

A-0363.thumb.JPG.7191c6dbaf2e5dc55606a578b4759277.JPGA-0364.thumb.JPG.15d6776fdf19c152195c9672aca52c63.JPG

Glenn (UK)

Posted (edited)

Build Log Index

Date: 23/09/2024

Time worked today: 1 hour.

Total time spent on build: 94hours.

 

Shroud Deadeye Installation Method and Failure

When I tackle a task which has a repetitive nature I like to find a method that will yield constant results. Adding deadeyes to the shrouds is one such process especially as I like to ensure the deadeyes are all set to the same height.

 

I came up with a method which helped me to set the shroud deadeye to the same height using a simple jig which I have used on several of my last builds with great success. It is a simple process, using a simple jig, and should ensure all the deadeyes are set to the same height.

 

There are two prongs which are used to locate the jig in channel deadeye. There are two sets of guide pins on the jig which are used to keep the shroud in place. There is a hole near the top of the jig which is used as the point where the deadeye seizing will start. The photo below shows the jig in place. The shroud has been placed between the top and bottom guides and I have used a spring clamp to provide a little bit of tension to the shroud.

A-0365.thumb.JPG.0bf2bbd7eefb37dbf37824dff4eb3ac8.JPG

The seizing thread, with the aid of a needle, is then passed though shroud and then through the hole in the jig. This reason for this is to ensure the seizing is set to the same place on each shroud line. In the photo below the seizing thread has been added.

A-0366.thumb.JPG.301e3493c7f2b2502e27ee791128ba2e.JPG

A loop for the deadeye is formed in the shroud which is then held in the quad hands so the seizing can be added, as can be seen in the next two photos.

A-0367.thumb.JPG.f8977e6d9c8d3a038950fa298e89fefd.JPGA-0368.thumb.JPG.69816d67776aad1d60de36674a7b904d.JPG

With the shroud still held in the deadeyes the seizing’s above the deadeye are added. In the photo below the first seizing has been added. I did add another seizing whilst the shroud was held in the quad hands.

A-0369.thumb.JPG.8ee028f84a98f5501984b7f30d5901b7.JPG

I then repeated the process for the second shroud. As can be seen in the final photo my tried and trusted method has clearly failed spectacularly this time around. I have no explanation why there is such a discrepancy between the height of the first shroud pair. I will remove the deadeyes from these two shrouds and start again. I am also going to think if I can refine the process to prevent such a error occurring.

A-0370.thumb.JPG.d2b7029af8e1586959f4afff3d8e9076.JPG

Edited by Glenn-UK

Glenn (UK)

Posted

Build Log Index

Date: 25/09/2024

Time worked today: 2 hour.

Total time spent on build: 96hours.

 

Fore Shroud Deadeye Rework

As reported in my last post I was not happy with how the first two fore shroud deadeyes looked, they were not set to the same height, even though the process detailed in my last post usually worked.

 

After carefully unpicking the various seizing threads I started the process once again, with a slight refinement. Using the same jig to determine the deadeye position in the shroud line I inserted the seizing thread to all 4 shroud lines and checked they were all at the same level. The next photo shows the seizing threads in position.

A-0371.thumb.JPG.fa95b7a4f24e6d66cf74eed0ecfa6796.JPG

With the first two deadeyes inserted in the shrouds the level of the deadeyes was checked. This time around I was much happy with how they look.

A-0372.thumb.JPG.5408881f285a3e90aa2bfd0644c8f56a.JPG

Confident that the process was working the remaining deadeyes were added to their respective shrouds and the seizing added. As can be seen in the next photo the deadeyes are reasonably level with each other. The lanyards still need a bit of tiding up however.

A-0373.thumb.JPG.34d63eb2161e22203ef73a4ccbce8588.JPG

I will now repeat this process for the other shroud lines.

 

 

Glenn (UK)

Posted
11 minutes ago, kgstakes said:

The work you do is amazing!!  I’ve done some crazy modeling before but I’m not sure I would have the patience ( or eye sight🤪) to do all the rigging you’ve done.

 

 Great job!!!

Many thanks. My patience does get near to breaking point quite often. 🤣

Glenn (UK)

Posted
5 minutes ago, Glenn-UK said:

Many thanks. My patience does get near to breaking point quite often. 🤣

That’s the natural order of things for rigging isn’t it, well it is for me as well! 🤣

Andrew
Current builds:- HM Gun-brig Sparkler - Vanguard (1/64) 
HMAV Bounty - Caldercraft (1/64)

Completed (Kits):-

Vanguard Models (1/64) :HM Cutter Trial , Nisha - Brixham trawler

Caldercraft (1/64) :- HMS Orestes(Mars)HM Cutter Sherbourne

Paper Shipwright (1/250) :- TSS Earnslaw, Puffer Starlight

 

Posted

Build Log Index

Date: 25/09/2024

Time worked today: 4 hour.

Total time spent on build: 100hours.

 

Main and Fore Mast Shroud Deadeye

The deadeyes have now been added to the fore and main mast lower shrouds and I am happy with how they look. For the most part my method for setting the position of the deadeyes to the same height within the shrouds worked very well.

 

Photo of Starboard Side Fore Mast Lower Shroud Deadeyes

A-0374.thumb.JPG.4e97343b628b9b3e84f166892e28332b.JPG

Photo of Starboard Side Main Mast Lower Shroud Deadeyes

A-0375.thumb.JPG.2446245f5e79878f1abb3f574276776a.JPG

Photo of Port Side Main Mast Lower Shroud Deadeyes. It will not take me long to add the shroud seizing’s.

A-0376.thumb.JPG.50af86aefdc84b3da8fb56086eb3adfd.JPG

Despite thinking I have a full proof method for setting the shroud deadeyes to the same height something went awry with the two leading deadeyes as can be seen in the next photo. These were the last two deadeye fitted, some maybe I rushed the process.

A-0377.thumb.JPG.f818175659a11ac328fb80d057b846d2.JPG

I reworked the offending two shroud deadeyes and I am now happy with how they look. It will not take me long to add the shroud seizing’s.

 

Port Side Fore Mast Lower Shroud Deadeyes

A-0378.thumb.JPG.537d0ca7ba570b4f823e095ab7eacc9f.JPG

Glenn (UK)

Posted (edited)

Build Log Index

Date: 30/09/2024

Time worked today: 2 hour.

Total time spent on build: 102 hours.

 

Lower Mast Stays

I thought I would share the method I am using to add the lower stays and preventor stays for the main and fore masts.

 

I started this process by cutting 4 lengths of black thread for the fore and main stays and preventor stays. Each of these threads requires a deadeye to be added. I used my quad hands to complete this activity.

 

In the first photo the deadeye and thread has been positioned in the quad hands. I am aware that the threads are fuzzy in the following photos but this will be sorted out.

A-0379.thumb.JPG.f593dbb511e12a16b5624250c0c68380.JPG

As per normal I am using a series of crossover knots for the seizing. In the next photo I have just started to add the first seizing.

A-0380.thumb.JPG.c833abfa2f1f70f9b5c2927127175f4e.JPG

In the next photo the first seizing sequence has been completed. I used 5 lower and 5 upper crossover knots.

A-0381.thumb.JPG.4e5661a648ac68063fe3d094ef42c8bf.JPG

The next two photos shows a stay with both completed seizing's.

A-0382.thumb.JPG.0b56527e553010c7a4f75db03e95a1ad.JPGA-0383.thumb.JPG.b5d1141e3a2a8a489bf6bef417ef7590.JPG

I am not a fan of the kit supplied mouse’s and I much prefer to make my own. This is quite easy to do. After determining the approximate position for the mouse I use a length of 0.25mm black thread to add a sequence of 5 lower and 5 upper crossover knots. This is shown in the photo below.

A-0384.thumb.JPG.6eba620e8f91532f8be8995c64bb0267.JPG

Using the same thread I then add a series of 3 lower and 3 upper crossover knots centrally on top and then a single sequence centrally on top. The completed mouse is shown in the photo below. The complete mouse can slide up and down the stay if required.

A-0385.thumb.JPG.1bbbe3f96f7a7c9d6b790a3603c05b2a.JPG

A loop is then added to stay using the crossover knot method. This ensures the seizing and loop size can be adjusted as necessary.

A-0386.thumb.JPG.27a4e4799f3b9a307177348ccfd4e747.JPG

The completed stay is then added to the mast so the position of the mouse and loop can be adjusted as necessary, as can be seen in the next photo.

A-0387.thumb.JPG.46ce44aa6c1d933637065c20e511dd10.JPGThe lanyard is also test fitted to check if further adjustments are necessary.

A-0388.thumb.JPG.00ae6aee91bd9b47fe5345d11956c6ca.JPG

The final three photo’s shows the completed test fitting of the fore mast stay and preventor stay. I am happy with how they look.

A-0389.thumb.JPG.9ba579ab7c872e97f35422aa03bcfa9b.JPGA-0390.thumb.JPG.623cfb50041a6892a1126741acb4c4a4.JPGA-0391.thumb.JPG.39158d5d5a6dff9d8d344dd4dc5e7e2d.JPG

Edited by Glenn-UK

Glenn (UK)

Posted

Build Log Index

Date: 02/10/2024

Time worked today: 6 hour.

Total time spent on build: 108 hours.

 

Main Mast Stays, Topsail Masts and Jibboom Guys

It has been an eventful two days. I thought I had completed adding the main mast stay and preventor stay and took a photo to show the progress.

A-0392.thumb.JPG.8ff2cfe88bb08d0b5ced086d6c74c21e.JPG

The next two photos shows the deadeye lanyard rigging for the main stay and main preventor stay.

A-0393.thumb.JPG.e0a2cccfbdadf496575f1db09d170a67.JPG

 A-0394.thumb.JPG.04cc4a6e7dcd51807f0c54d61a9a7e44.JPG

On closer examination I noted that I had made a couple of errors. The preventor stay should wrap around the top of the main mast, as indicated by the yellow arrow in the next photo. If you look closely, as indicated by the blue arrow, you will see I failed to do this. The red arrow shows that one of the main mast shroud lines is twisted.

A-0395.thumb.JPG.916b18f114c720db3db61c0fb7ef7e68.JPG

It took me around 30 minutes to redo the preventor stay and twisted shroud line. Now that I was happy with my work the main and fore topsail masts were added.

A-0396.thumb.JPG.d2f4143e8179a5c7bed50651616b7c90.JPG

I decided to add the jibboom guy. This should have been a fairly straight forward task. The two guys (left and right sides) are secured to the end of the jibboom and then pass through eyelets located on top of the spritsail yard and are then secured to the hull via a double block arrangement. On completion of this task I took a photo and noted two errors which I have highlighted with arrows in the next photo.

A-0397.thumb.JPG.fd2136204f9076753fd907526d70c6cd.JPG

The most obvious error is I used the wrong seizing thread when securing the right-hand side guy to the end of the jibboom. You can see the difference in the next photo, green is OK, red is not OK.

A-0398.thumb.JPG.02877e8e4b7cd70ff9327efe9fa697bd.JPG

The double block arrangement is not symmetrical. The left-hand side is the better arrangement in my opinion.

A-0399.thumb.JPG.58fc6fbbc9b1130e7cc84ef0dd3d43a1.JPG

The right-hand side needs to be redone as the gap between the two block is to close in my opinion and compared with the left-hand side.

A-0400.thumb.JPG.6edf049a0a772c55a3aa798ee3940891.JPG

Glenn (UK)

Posted

Looks great Glenn. Be careful of those eyelets at the end of the jib boom. Being clumsy I snapped three of them off the main ring by accident… 

Dan

                                                                                                                                                                                                                                      

Current Build: Yacht Duchess of Kingston (Vanguard Models, 1:64)

Previous Builds: Fifie (Vanguard Models, 1:64), Nisha (Vanguard Models, 1:64), Zulu (Vanguard Models, 1:64), Saucy Jack (Vanguard Models, 1:64), Erycina (Vanguard Models, 1:64), HMS Alert (Vanguard Models, 1:64), Grecian (Vanguard Models, 1:64), Ranger (Vanguard Models, 1:64), HM Gun Brig Adder (Vanguard Models, 1:64)

Waiting to be Built: Speedy (Vanguard Models, 1:64)

Posted (edited)

Build Log Index

Date: 06/10/2024

Time worked today: 4 hours.

Total time spent on build: 112 hours.

 

Topsail Mast Shrouds Part 1

As is the norm over recent weeks I seem to be doing plenty of rework. Some is due to silly errors on my part and some due to my completed work could be done much better. This theme has continued with my work on the topsail mast shrouds.

 

I started the process by cutting the required lengths for all the topsail shrouds and then proceeded to make the loops so they could be added to the topsail mast. So far so good!

A_401.thumb.JPG.d83168d50d8e45c35fafc57b3bdf3a8c.JPG

When I did a test fit of the shrouds, I noted two problems. When looking at the next photo the two problems are:

a)      The shrouds are sitting on top of each other, and it is not possible to position them side by side. The reason for this problem is the seizing thread used was to thick

b)      The seizing also needs to be positioned to just below the crosstrees as there not enough room between the crosstrees otherwise.

A_402.thumb.JPG.bdf4935cad60c98243a3ccc6a40a7c69.JPG

The seizing was redone using thinner 0.1mm black thread and looks much better.

A_403.thumb.JPG.494a277979c8f8c887ab317e9dcb4964.JPG

With the seizing was positioned below the crosstrees it looks much better on the Indy.

A_404.thumb.JPG.bb67c23329c9876366c2bab897a3591d.JPG

When adding the deadeyes to the shrouds I have opted to try a new method, which is detailed below.

 

Step 1 – Make a loop and position in the quad hands.

A_405.thumb.JPG.16302ecee298a431551844a629eece1d.JPG

Step 2 – Use a simple crossover knot start to the seizing

A_406.thumb.JPG.0d02bf8105d9bdeded7ac29849dffd8b.JPG

Step 3 – Loop the seizing thread around and make a second crossover knot

A_407.thumb.JPG.9c71aa2ddc7b55748d220680b4d5e982.JPG

Step 4 – Repeat step 3 once again.

A_408.thumb.JPG.946f4a815f0d5162c6f74ac4601176e4.JPG

Step 5 – Adjust the position of the loop to the required position.

A_409.thumb.JPG.4cfdca082ea6058ef2f3f78cbe98cc1d.JPG

Step 6 – Close the loop around the deadeye and adjust the position as necessary.

A_410.thumb.JPG.2bb88fe752786870ddac625eee8cd309.JPG

Step 7 – Check position of the deadeyes are level using the quad hands.

A_411.thumb.JPG.66877641d53cb94c83254629b4bd4eae.JPG

Step 8 – After a test fit on the Adder to check the deadeyes are in the right position and look level with each other add the additional seizing. Note: I did test fit the lanyards to check the deadeye positions were OK.

A_412.thumb.JPG.87e2b8022172bf0acc02ef294c0195bc.JPG

I will add more photos when I am ready to add the lanyards.

Edited by Glenn-UK

Glenn (UK)

Posted

Build Log Index

Date: 09/10/2024

Time worked today: 4 hours.

Total time spent on build: 116 hours.

 

Topsail Mast Shrouds Part 2

Work has continued with the topsail mast shrouds. Following on from my last post the next stage in the process was to quickly check the shrouds with the lanyards to see if any further adjustments are necessary. I am using clamps to hold the strops in place for the time being.

A_413.thumb.JPG.42222aba8770d5a65da7bd1d0e1da92a.JPGA_414.thumb.JPG.8903dbb9deb53aea26bd4e74e769be09.JPG

Happy with how they were looking I went ahead to glue the strops in place and then completed the shroud seizing.

 

When I did the next test fit typically one of the shrouds did not look very good and I did notice its deadeye was upside down. Pity I did not notice a more fundamental problem. More on that later in this post.

A_415.thumb.JPG.d88eac1e351969327f4c6d09b2f08b94.JPGA_416.thumb.JPG.6470264f6dc81317761ceb331adc941b.JPGA_417.thumb.JPG.3a1440edb8e93ca4a5f7d964e63f8112.JPGA_418.thumb.JPG.1f1933f4eb01a18e61f5effa969af0d9.JPG

A block has to be fitted between the first and second shrouds which is used for the yard lifts.

A_419.thumb.JPG.f576959b8e6f9c3280fb1cf42b6b169f.JPG

It is easier to fit these blocks before the shrouds are fitted. With the block placed between the first two shrouds it is held in position using my quad hands so the seizing could be added.

A_420.thumb.JPG.b93755c98930bde7478b51d53fb606db.JPGA_421.thumb.JPG.0e406f4a18471c82ec6eea4a42b4b005.JPGA_422.thumb.JPG.8202917d876cf57bf1173466fc967aba.JPG

When I started to complete the rigging I finally noticed that I had made a big school boy error when I added the deadeyes to the strops.

A_423.thumb.JPG.c385af39c7ccbf6ecb0547b137bc8cd8.JPG

The deadeyes were pretty firm in the strops, and I was unable to rotate some of them when I tried. I then tried to release the strops from the platform, using a bit of acetone to loosen the glue. I ended up damaging the platform edge when I finally released the first strop. Therefore I have decided to live this error for this model, as once built it will not be on display.

 

Glenn (UK)

  • 2 weeks later...
  • 2 weeks later...
Posted

Build Update

I have had an enforced 3 week break from building this model. It started when I had an offer to sell my model of the Indy. I took a few days to dust her down and to build a suitable shipping frame. I also hand painted the figure of Captain Pellow.

 

Unfortunately she suffered some damage when the buyer tried to fit her in his car,. It then took me a week to repair the damage, which required two new topgallant masts (Main and Fore) and then removing and then replacing all the topgallant mast and yard rigging.

 

I also had a weeks holiday in France in the middle of all of this mayhem.

 

The repaired Indy has now been delivered to the buyer intact, using a specialist delivery company (Lenspeed).

 

Therefore today I was finally able to return to the Adder build and I will be able to start posting my progress later this week.

Glenn (UK)

Posted

Build Log Index

Date: 05/11/2024

Time worked today: 4 hours.

Total time spent on build: 120 hours.

 

Topsail Stays

To start this post I have attached a photo showing the current build status of my adder.

A-424.thumb.JPG.00d40c1711ab4e3a6b634ab75fc817f9.JPG

I have now added the topsail mast stays and the back stays.

 

The topsail stays are belayed to the deck via a two block arrangement. The lower block is a single block secured to the deck (main) and hull (fore) via an eyebolt. The inter-block rigging is added to these blocks via an thimble. A double block is added to the end of the stays.

 

I started the process by adding the double block to each of the stays. To do this I make a loop in the stay.

A-425.thumb.JPG.81711e4098e6650105ec3f976dc22c1f.JPG

The loop is then closed around the block and its position can be adjusted up or down the stay as necessary. As can be seen in the next photo I am checking the position which is just about where I want it to be.

A-426.thumb.JPG.6a8c1abb0ff320ff6dea5dd919097841.JPG

Once I was happy with the positioning of the block a second set of seizing was then added.

A-427.thumb.JPG.2551c27c4682738ab36539a1a1bce64f.JPG

Once that was done the single blocks were seized to the eyebolts and then secured to the deck / hull. Adding and belaying the inter-block rigging was then a straightforward task.

A-428.thumb.JPG.b8992787370f66c3f6ee8457924c0256.JPG

The belaying of the main and fore mast stays have also been completed.

A-430.thumb.JPG.6daba36d1c3fe2ccec8fdd5d23a8a15b.JPGA-431.thumb.JPG.385a5eee73002c738a4efbbd46cd9fa3.JPG

And finally another photo of the Adder

A-432.thumb.JPG.45facad209c9cb9dc53480e9041d7090.JPG

I will now start work on adding the topgallant masts and shrouds.

A-429.JPG

Glenn (UK)

Posted

Build Log Index

Date: 08/11/2024

Time worked today: 4 hours.

Total time spent on build: 124 hours.

 

Futtock Staves and Catharpins

I have started to add the futtock staves and catharpins. When adding the futtock staves I used the quad hands to hold the staves in place.

A-433.thumb.JPG.053b09483a5308f7f93ccae86c3d4520.JPG

I did use a template to make to help position the staves.

A-434.thumb.JPG.c2e36e8e9e036812ab326314f1262006.JPG

It was then a case of securing the stave to the shrouds. In the photo below I have secured the staves both ends. I did secure the stave to the middle two shrouds after I took the photo

A-435.thumb.JPG.72680e0a523e5cbf0547d85057d0d91b.JPG

The quad hands were used when adding the catharpins. With the one end of the catharpin thread wrapped around the stave I was able to add the seizing.

A-436.thumb.JPG.01de0619d909b21241bbfa569abd498e.JPG

It did not take two long to complete the process.

A-437.thumb.JPG.079a9ff30bb72b7e863d31e616768480.JPG

The next task was to add the ratlines. I used a template for this.

A-438.thumb.JPG.ff763eacf16cf486bb62c837d632a166.JPG

I added the ratlines above the stave first.

A-439.thumb.JPG.0bfc043d8544923e55f170a20b912dca.JPG

I did mark the template to help with the positioning. When adding the ratlines added all the 1's followed by all the 2’s and then finally all the 3’s.

A-440.thumb.JPG.830fe4017205ce85efb6ad252a1a8f5f.JPGA-441.thumb.JPG.40cfefb1a93b5a02259b6cd14e01bdab.JPGA-442.thumb.JPG.af8e0aa7a0c27dee9965a3f161d948d6.JPG

The final task is to add the futtock shrouds, these have been prepared and are ready to be installed.

A-443.thumb.JPG.1714882c30a6f064b1185bef881704da.JPG

Glenn (UK)

  • 2 weeks later...
Posted

Build Log Index

Date: 19/11/2024

Time worked today: 10 hours.

Total time spent on build: 134 hours.

 

Shrouds, Ratlines, Stays and Backstays

I have finally completed adding all the shrouds and ratlines. I have also completed all work related to the stays and backstays.

 

I find it is difficult to take good quality photos at this stage of the build process. I have attached a couple of photos showing the current build and a three showing some of the rigging.

 

I will now look at adding the running rigging for the driver boom and gaff boom. Once that is done it will time to add and rig all the masts. This means the end is now in sight and it should tie in nicely with my next project as I now have the Harpy on pre-order with Vanguard Models.

A-439.thumb.JPG.97d2512484ad49b5e1a9bc85a026da33.JPGA-440.thumb.JPG.0b0599a078e70d1883897a666025b228.JPGA-441.thumb.JPG.2b43fe48ba3f80b96ea69962dc4a0018.JPGA-442.thumb.JPG.04422419e3f0d472432f3554823fdd77.JPGA-443.thumb.JPG.ca8c8d28c0737b861d46a1ff6d9f0b96.JPG

Glenn (UK)

Posted

Build Log Index

Date: 19/11/2024

Time worked today: 2 hours.

Total time spent on build: 136 hours.

 

Driver Boom Running RIgging

This was a mundane and simple task to complete.

A-452.thumb.JPG.56e4572c9ae5ddc844c883cdef91e9ee.JPG

Step 1

The driver boom was added to the main mast as shown below.
A-444.thumb.JPG.02339bde0e6da7f487c25c5ed026122c.JPGStep 2

The inter-block rigging, shown in the next photo was then added, but not belayed.

A-445.thumb.JPG.024df8687f974f8d24f0cb87ffdc290f.JPG

Step 3

Next a length of thread was added to the end of the driver boom.

A-446.thumb.JPG.e01459302fe4c16d77f9e9ed13a641c4.JPG

Step 4

This thread was then reeved through a block on the main mast.

A-447.thumb.JPG.a99366c65bb24c3c8f139a41cd577999.JPG

Step 5

The first inter-block block was then belayed.

A-448.thumb.JPG.fef42c9a54ee33d91ae33b552e8197ee.JPG

Step 6

The thread from the end of the driver boom was then belayed to deck, via a double block arrangement, as shown below.

A-449.thumb.JPG.2a8e11024b9b88df3eded584250d4a76.JPG

Step 7

The final task was to add a second thread, as shown in the next two photos

A-450.thumb.JPG.ddf282030b07ace6e56408bb4424617c.JPGA-451.thumb.JPG.1d6c8fd120cec9825627e5eb137bb9a9.JPG

Glenn (UK)

Posted

Build Log Index

Date: 19/11/2024

Time worked today: 2 hours.

Total time spent on build: 136 hours.

 

Driver Boom Running RIgging

This was a mundane and simple task to complete.

A-452.thumb.JPG.56e4572c9ae5ddc844c883cdef91e9ee.JPG

Step 1

The driver boom was added to the main mast as shown below.
A-444.thumb.JPG.02339bde0e6da7f487c25c5ed026122c.JPGStep 2

The inter-block rigging, shown in the next photo was then added, but not belayed.

A-445.thumb.JPG.024df8687f974f8d24f0cb87ffdc290f.JPG

Step 3

Next a length of thread was added to the end of the driver boom.

A-446.thumb.JPG.e01459302fe4c16d77f9e9ed13a641c4.JPG

Step 4

This thread was then reeved through a block on the main mast.

A-447.thumb.JPG.a99366c65bb24c3c8f139a41cd577999.JPG

Step 5

The first inter-block block was then belayed.

A-448.thumb.JPG.fef42c9a54ee33d91ae33b552e8197ee.JPG

Step 6

The thread from the end of the driver boom was then belayed to deck, via a double block arrangement, as shown below.

A-449.thumb.JPG.2a8e11024b9b88df3eded584250d4a76.JPG

Step 7

The final task was to add a second thread, as shown in the next two photos

A-450.thumb.JPG.ddf282030b07ace6e56408bb4424617c.JPGA-451.thumb.JPG.1d6c8fd120cec9825627e5eb137bb9a9.JPG

Glenn (UK)

Posted

Build Log Index

Date: 20/11/2024

Time worked today: 4 hours.

Total time spent on build: 140 hours.

 

Gaff Boom and Main / Fore Yard Jeers

Adding the running rigging for the gaff boom was a bit more involved compared with the driver boom but not to taxing. With the gaff boom secured to the mast via the parrel beads all the other running rigging was installed and adjusted and belayed. I was happy with the result.

 A-453.thumb.JPG.f4d725415c5d64058807494cf1eb80b4.JPGA-454.thumb.JPG.a8e011742210a51cc85c60b29cfdc1b4.JPGA-455.thumb.JPG.81d0afa02caea8eb5697dcad554223ce.JPGA-456.thumb.JPG.39a3dce5dc20ae5ef62ac96d02a0e298.JPGA-457.thumb.JPG.0aaddaaf121a4a5664f152931a9ffaf6.JPGA-458.thumb.JPG.dc61627687005f7669758159b6d3d362.JPG

I then secured the main and fore yards to their respective masts and added the jeer rigging.

A-459.thumb.JPG.5330003d4dc0231d86f4eebe8e583d3c.JPGA-460.thumb.JPG.dc2f3af889aa4990751648b4cdcc38df.JPG

 

Glenn (UK)

Posted

MY FINAL BRIG ADDER BUILD LOG POST
I had about another weeks work left to complete the Brig Adder as I only had the yard braces and lifts to rig. This would have tied in nicely with the expected release date for the Harpy, which is my next build project.

 

Unfortunately when I started work on the Adder this afternoon I noted the fore topgallant mast had been damaged, I can only assume I knocked yesterday when I was adding one of the fore topsail yard jeers. After trying to repair the damage I ended up making matters far worse and realised that I would  have to remove fore topgallant mast and all of its associated rigging. Once that was done I would then have to make a new topgallant mast and redo all the rigging.  I know from experience, with the Indy, that this is not an easy repair. The most difficult aspects are trying to remove the damaged mast from the end cap and the shroud rigging that is belayed around the topsail deadeye strops.

 

This is a photo of the damage.

A-461.thumb.jpg.a37eb0cc45c718a1a2cb716d43bef0d0.jpg

I have really enjoyed building the Brig Adder but my interest in model boats, as a hobby, is the building process and developing methods to make the building process easier.  I was so pleased when someone bought my Indy as there is no room left in the house to display all of my completed models. At the moment I have two small Vanguard Models fishing boats on display on the living room. The Sphinx is on display in the dining room and both the Alert and Duchess of Kingston are on display in the conservatory.

 

I have decided to stop work on the Adder;

a) I do not have the space to display the Brig Adder when completed

b) My next build (Harpy) is due to released in the next week or two which I will want to start immediately.

c) I do struggle with some aspect of the rigging due to my poor close vision

d) I may end up doing more damage when I try to remove the damaged mast and associated rigging

 

Thank-you to everyone who has been following and commenting / liking my Brig Adder build log posts it is greatly appreciated. Many thanks also to @chris watton for designing and selling this amazing kit and I am sorry Chris that I have sadly failed to cross the finish line when I was so close to the end. I have already downloaded then Harpy manual so my free time will be spent reading the manual and checking out @James H excellent Harpy build log.

 

 

Glenn (UK)

Posted

Sorry to hear. It is difficult to do a quick fix. Did you consider drilling into each end then putting a pin to help stabilize for the clamps and glue to dry ? Would not take long to try.  Hate to see such a lovely build put up in ordinary as they would say.  Look forward to your next one.

Posted
10 minutes ago, ECK said:

Sorry to hear. It is difficult to do a quick fix. Did you consider drilling into each end then putting a pin to help stabilize for the clamps and glue to dry ? Would not take long to try.  Hate to see such a lovely build put up in ordinary as they would say.  Look forward to your next one.

The damage was where the topgallant yard was pinned so not reallt possible to add a pin with repositioned the topgallant yard. I did consider a few different options.

Glenn (UK)

Join the conversation

You can post now and register later. If you have an account, sign in now to post with your account.

Guest
Reply to this topic...

×   Pasted as rich text.   Paste as plain text instead

  Only 75 emoji are allowed.

×   Your link has been automatically embedded.   Display as a link instead

×   Your previous content has been restored.   Clear editor

×   You cannot paste images directly. Upload or insert images from URL.

  • Recently Browsing   0 members

    • No registered users viewing this page.
×
×
  • Create New...