  1. In preparation for fairing the hull I added some supports to the bulkhead extensions. Some of these are less than an 1/8" wide and are a too flexible, I think. Eventually they will be reduced to a 1/16", but not until some planking support is in place.

    _DSC8327.thumb.jpg.f680d01416bcaf5367812705cbf5b153.jpg

    Fairing the hull was straight forward using various sandpaper sticks along with a lot of batten checking. It will be faired again after the gun port sills and lintels are in.

    _DSC8322.thumb.jpg.236462def2d0a9a15f889806ee2d54aa.jpg

    The bow filler pieces needed a lot of attention. The curve changes constantly as it moves up the stem and many checks with a batten were necessary to get the fit right. I also started work on the gun port sills. A batten was used to establish a smooth flow of sills along the hull while using the reference lines that are etched onto each bulkhead as a guide. Slight variances were visible once the batten was pinned to the hull. After making final adjustments, a sharp pencil was used along the top of the batten to draw the final sill locations on the edge of each bulkhead. The batten was then removed.

    _DSC8324.thumb.jpg.f7b566ba07c6d5a06af5e04988085a06.jpg

    When adding a gun port sill, a temporary batten was clamped to the opposite side of the hull. The top of the batten is flush with the sill locations drawn on each bulkhead. Though not shown here, I used a 3/8" wide cross-spall across the batten to the other side of the hull where the new sill was located. Pressing the sill to the cross-spall, while holding the cross-spall against the batten, flattens the upper edge of the sill parallel to the other side.

    _DSC8326_sfw.thumb.jpg.bc5da487aeb76969e102b263071e80e6.jpg

    _DSC8328.thumb.jpg.fbf2d662faf3d26f5f5d1717bb10c615.jpg

    Mike

  2. 14 hours ago, dvm27 said:

    Once the fore end of the plank was secure on the hull it was relatively easy to glue in the rest of the plank, repeating the above technique every inch or so. This way you are only dealing with short sections of curves or twists at a time. It is time consuming but worked quite well for me.

    Sounds familiar, Greg! Though I found it easy enough to hold the plank tip into the rabbet using carpenters glue, until set, instead of using CA.

     

    Mike

  3. Hello everyone! Since my last post I have been contemplating whether or not my using Cherry as the primary wood was the right choice for me. No doubt some beautiful ships have been built from Cherry, but I really prefer the look of boxwood. I thought about removing just the knee and keel assembly, but quickly ruled that out. The problem being that it would be difficult aligning those new parts to the already assembled bulkhead former/bulkhead assembly. This meant that I would have to start over from the beginning. So, over the last few weeks I have managed to re-build her with boxwood.

     

    Right now, 3/16" laser cut boxwood kits are not being offered for the Winnie. The nine pieces making up the knee parts were scratched from 3/16" boxwood sheet. The mill came in handy for making the bobstay holes and gammon slot.

    _DSC8301.thumb.jpg.326b1d429a600f89e136477acdf9ed38.jpg

    I'm going with copper bolts this time. Blackening will be done later.

    _DSC8306_sfw.thumb.jpg.f7acf38cbffe7eab2ae27694938f4042.jpg

    Large blocks were used to handle any slight twists in the bulkheads while at the same time keeping the structure straight.

    _DSC8309.thumb.jpg.4bc64a1338ac154339f82d1747b2bbfa.jpg_DSC8311.thumb.jpg.86fb5308ea0d4ebea9a86c9437aa1612.jpg

    The two lower platforms were added as well.

    _DSC8308.thumb.jpg.e5445ba4e6c051b4de51a47de246f6a8.jpg

    _DSC8310.thumb.jpg.2556980a2fc66f43cf15a994f361c44e.jpg

    Mike

  4. Made a bit more progress today by simulating the lower stem and keel bolts. Holes were drilled with a #76 bit and filled with .017 black monofilament and PVA glue. I'm not a big fan of CA as it has a tendency to discolor the wood.

     

    I anxious to see what the Cherry will look like after a coat of W-O-P. I should know soon enough.

    _DSC8294_sfw.thumb.jpg.081c1b54c70ee4e861f64b210ce4705d.jpg

    _DSC8295_sfw.thumb.jpg.3285d940af9603ffd2152bf35ab9bf5e.jpg

    Mike

  5. In preparation for making the false keel, the keel bottom was sanded 90° to its adjacent edge and smooth across its bottom face. To do this, I first raised the bulkhead former/keel assembly off the flat surface with 1/4" flat sheet. I used a square sanding block, gliding along the flat surface of the board to sand the edge.

    • _DSC8286.thumb.jpg.94a50e432f6c78d2559e176ca6acd47b.jpgThe false keel was ripped on the table saw from some scrap Cheery that I had lying around. It's made in three sections joined with what I think is called a "Harris joint". As you can see, I located the joint far enough away from the keel joint._DSC8290_sfw.thumb.jpg.e6235c7f241b6d2917d3733e4282e3ab.jpg

    _DSC8293_sfw.thumb.jpg.1c9b32ded768ccf5e2e5e3b9b8e647fb.jpg

    In preparation for adding the bulkheads I made the build board that will hold everything upright and straight._DSC8292.thumb.jpg.99d95d0f7734fa1e8ec977135bf56920.jpg

    Mike

  6. Snowy nights are a perfect time to get back into the workshop.

     

    The bulkhead former is now in one piece. These laser cut parts were joined with Elmer's Carpenter glue without any prior sanding on the joints.  A slab of flat marble was used to rest the parts on while the glue set.

    _DSC8267.thumb.jpg.a5a4b2e128aa8ad10f8a212cbd45fb41.jpg

    The bearding line is laser etched into one side of the former. I traced the line and transferred its shape to the other side using graphite paper.

    _DSC8259.thumb.jpg.b5b58c0bdfa2e07ea2b32c55a14ea73b.jpg

    _DSC8262.thumb.jpg.d5c0388582c32cd633311f0c52fc6dd2.jpg

    The rabbet is 1/16" x 3/32" strip which was cut from 3/32" boxwood sheet. The fore side was moistened and heat bent into shape with a blow dryer. _DSC8266.thumb.jpg.ec4cb3103dd5ad55842e29b13ab0217d.jpg

    Since the former is rather long the rabbet strip was made in two pieces joined with an angle joint for strength. This joint also makes it easy to align the next section, simply by slipping it under the first section.

    _DSC8269.thumb.jpg.b33133a040aae5a87f22c47fdc50a56b.jpg

    The completed rabbet with a small section also added to the aft area of the former.

    _DSC8270.thumb.jpg.bb3ef78058176a4d36c49a3f85fe0284.jpg

    Mike

  7. With the upper deck clamps completed I was able to install the keelson. Lengths of pine were pushed down by strips that I passed athwartships through the spaces between the frames, thus holding the keelson down tight to the floor timbers while the glue sets. With the keelson in place bolts were inserted and peened down tight into the floors timbers.

    _DSC8224.thumb.jpg.d9cfa673ab1ecc217ec9ac2633df05a9.jpg

    _DSC8226.thumb.jpg.5436e07a11d330bb3709437229bd6633.jpg

    Mike

  8. The keelson has all three sections joined and sanded to shape, though not glued to the frames yet. I will need to drill holes for the bolts which will go through each floor timber and install the two upper deck clamps first.

    _DSC8219.thumb.jpg.43c7950334eccb7277f55acfc0ae2116.jpg

    The upper deck clamp is 4" thick (.083 actual). It is made in three sections joined by two scarph joints. The fore section had to be steam bent into shape. The other two sections were shaped with dry heat. The height of the clamp was carefully measured at several stations (frame locations) on the draught. Those measurements along with adjustments necessary to account for the beam heights were then transferred to the frames with the aid of a height gauge. I attached a piece of strip wood to the gauge that was thin enough to fit between the frames.

    _DSC8216.thumb.jpg.7a27cc6e42868c46b348f06fa9c32ce0.jpg_DSC8215.thumb.jpg.28cab99d70e9cce0c537b94630ad64da.jpg

    Looking at the these photos, it appears that the clamp is sloping downward as it turns inward near the transom. Before going into panic mode I decided to check this out for myself. I placed a batten along the top edge of the clamp while eyeing it from the rear of the ship. Turns out it's just an optical illusion. With the port side completed these frames are now quite strong compared to before. _DSC8222.thumb.jpg.940a27f1496fa5b7a716635974e2b903.jpg_DSC8221.thumb.jpg.0c67d8d77c77c724783c5930e20f463f.jpg

    Mike

  9. druxey: Some of those steps in the floors are more than slight. I don't mind the extra sanding if it insures that the frames are not cut too thin to begin with.

     

    Kurt: A lot of these frames have glue squeezed out. I disc sanded one frame smooth and almost took off too much wood. So, I kinda gave up on that idea. Besides, I love sanding wood!

     

    Mike

  10. Thank you all for your comments and "Likes"

     

    My plan for fairing the frame floors. .

     

    I started fairing the inner hull at the toptimbers which was easy enough. As I moved down toward the frame floors, I realized that I had to establish the height of each floor above the building board while getting the overall slope to match the shape of the keelson. To do this, I decided to make the three section keelson, using each section as a sanding block. Each section was left quite a bit higher so I would have something to hold onto. Sticky back sandpaper was adhered to the bottom face. So, after adding a number of frames, moving the block back and forth, in very short strokes, eventually brought the floors down to match the keelson shape. Floor heights were checked above the drawing board as sanding progressed.

     

    Aft section test fit

    _DSC8204.thumb.jpg.46da6e2f4084420fd40eb822435d25f7.jpg

    Moving ahead, I added the middle section of the keelson. Sandpaper was added to the middle section and five layers of blue masking tape added to the aft section which matched thickness of the sandpaper. Now I could sand down those frames forward of the aft section without affecting the work already done.

    _DSC8207.thumb.jpg.bae191836e6592c5e25da032a0d57ce2.jpg

    Sanding leaves shallow notches in the floors that are too high. _DSC8209_sfw.thumb.jpg.4ce1e55fb146fc38237cf2c469377d24.jpg

    Test fit with two sections completed.

    _DSC8210_sfw.thumb.jpg.91348b7f52ad22713698c5d1cf402d6d.jpg

    Mike

  11. Happy New Year to all!

     

    I finally reach a milestone over the holidays, though I still need to do some additional fairing on the inner hull. Once that's completed, I will move onto to installing the deck clamps. They will help to stabilize the hull in preparation for the exterior hull fairing. 

    _DSC8199.thumb.jpg.7d0dc9149e2e2c4d573bb3ebf80c305d.jpg

    _DSC8201.thumb.jpg.804bf3ee9967e22a1b2c5ff13860ee88.jpg

    Mike

  12. Snowy day here in NY. . Four more frames installed and the usual internal fairing resumes. More work is needed on the previously installed frames to account for the downward slope of the floor timbers and changing angles.

     

    All of the frames are cut slightly wide of the drawings, both inside and out, leaving them quite rough looking. Toptimbers are made taller as well. Being my first POF build, I'm not taking any chances in making them too small. It means extra work in the fairing process, but better safe than sorry. Removing one of these would not be a fun. 11 more to go.

     

    Rifflers are my go-to tool to start things off. Battens insure that things stay smooth. _DSC8187.thumb.jpg.312b4b9644e6e2f58a4bf2592528903d.jpg

    Mike

×
×