Putting in his lunch order. 
 

But seriously….they are same figure and just used for scale.  I actually move him around as I develop the drawings.  Insane how tight the spaces were and low the ceilings were.  
 

I placed him near the tiller on the poop deck also…no railings port and starboard.  Crazy stuff…lucky if the bulwarks are knee high…

 

Just high enough to trip overboard.

 

workingdrawing2.jpg

 

workingdrawing3.jpg

 

Posted

This is optional of course as it might obscure the elegant curve of the sheer. 

 

But as I mentioned the bulwarks are not very high along the poop.  Having said that,  there would have been a rope railing and stanchions there.  In fact,  several drafts of similar sloops actually show them.  
 

You may add them if you really want to and it would be historically correct.

 

This is from a draft of “Fly” from the same year.  Note the stanchions.  There are other features shown on this draft which are not shown for Speedwell that could be used as well.  It all depends on how true to the contemporary model you want to be.

 

For example.  The ladder down to the lower platform.  Speedwell does not show one but who knows.

 

In addition..the swivel

stocks.  Which you will see Greg added but are not shown on the Speedwell contemporary draft.

IMG_1289.jpeg

Posted
15 hours ago, Chuck said:

I placed him near the tiller on the poop deck also…no railings port and starboard.  Crazy stuff…lucky if the bulwarks are knee high…

 

Ok, that's just shocking.  I'd nervous to steer that ship on a lake. lol

 

Alan

Posted
17 minutes ago, Freebird said:

Interesting details, but like you’ve said before, Chuck, less is more. 

For me that is very true...But some folks do like to "kitchen Sink" a model.

 

 

Posted
6 hours ago, Chuck said:

In addition..the swivel

stocks.  Which you will see Greg added but are not shown on the Speedwell contemporary draft.

I didn't actually notice that the swivel stocks were not on the original model Chuck. But the swivels ("ten 1/2 pounder swivel guns") are clearly noted in Winfield's British Warships in the Age of Sail 1714-1792 as specified for the Cruiser class. Of interest to us modelers is that only enough swivel guns to fit out one side was required. As they were so light they could be carried to the other side as needed.

Greg

website
Admiralty Models

moderator Echo Cross-section build
Admiralty Models Cross-section Build

Finished build
Pegasus, 1776, cross-section

Current build
Speedwell, 1752

Posted
54 minutes ago, dvm27 said:

But the swivels ("ten 1/2 pounder swivel guns") are clearly noted in Winfield's British Warships in the Age of Sail 1714-1792

Yes indeed.   I am however probably going to stick with the how the cont. model was portrayed.  Its easy enough to add a few more swivel stocks for folks who want to add them.  Builders choice.  Aesthetically, they just ruin the elegant run of the sheer to my eye.   If I were to include them however I would certainly add a rope railing with stanchions along the poop as shown on that draft detail I posted of "Fly".    I think it would make sense to my eye anyway.   But I am going to stick with just the few swivels mounted at the bow.  I have gone with the model for so many other things.....number and position of timberheads etc.  Although I have also been swayed on some other things shown on the original draft as opposed to the model.   Its a trade-off.   Once you start looking you will spot so many differences....between all of these primary source references.   I forget how many swivels you ended up with per side.   Seven or eight?  

 

The draft for Cruiser does show a heck of a lot more swivels...as shown below (bottom).   Just to show folks who will build the kit and want to go another way.

 

Cont model with two swivel stocks per side.

 

d4083_1.jpg

Speedwell draft with two swivel stocks per side.

originaldraft.webp

 

Cruiser class draft with 10 swivel stocks per side.  Very different appearance with the open sheer rails as well.

 

cruiser.jpg

Posted
12 minutes ago, druxey said:

Concerning the low/lack of bulwarks on the quarter deck, there would have been stanchions with man-ropes along the sides

Yes thats what I figured.  I usually dont have so many original drafts or

contemporary sources as is the case with Speedwell.  And when they are so different it makes for too many choices.  LOL

 

But she will be pretty when all finished no matter which way you choose.

 

Chuck

 

 

Posted

Starting chapter 7

 

The first thing I wanted to do, just to get it out of the way...was to get all the gundeck beams made.  I cleaned the char off of all 11 beams now.  Then they were cut to length using the plans as a guide.  I also used the plans to establish where each deck beam is positioned.  For now I will just set them aside and grab them as I need them.   The last thing I wanted was to have to stop what I am doing just to clean char off a beam and cut it to length.  Its a comfort knowing they are all done and ready.

 

The photo below shows all the beams just resting on the deck clamp.

 

gundeckbeams.jpg

This allowed me the opportunity to cut all the templates and see what the planking scheme would look like so I can adjust it now rather than later.   I think its a good plan as is...and I wont make any adjustments, yet.

 

gundeckbeams1.jpg

 

With the beams all ready and at hand, I could start making the cabins on the lower platform at the bow.

 

Each bulkhead will be made in two layers.   Both are 1/32" thick and are laser etched with a bunch of reference lines.   Now it would be easy enough to make these from scratch but this does make the building process quicker.  Especially since very little of these will be seen.  Below are the sections for the carpenters cabin on the starboard side.   It shows both sides.  I cleaned the char from the inside edges of the door panels and then glued up each layer.

 

Before I add any details I made sure they fit on the model.  I adjusted them to fit nicely in position and adjusted the heights etc.   This is why it is good to have those deck beams handy.  You need to have the first two beams in position to get the heights correct.

 

fcastlecabins.jpg

 

Once I was sure they fit on the model OK (see the deck layout for details), I started added the hinges and stanchions.

fcastlecabins4.jpg

First I added the upright timbers which are either 1/8" x 1/8" strips cut to length or 3/32" x 3/32" strips.  The plans show which.   Then I added the door handles and hinges.   Make sure to add the handles on both sides of the door.   And be careful to put them on the correct side based on which way the doors open.

 

The outside view of both bulkheads completed.

 

fcastlecabins1.jpg

The interior of the carpenters cabin detailed.

fcastlecabins2.jpg

 

Finally they were glued into position on the model.  I placed the side with the doors first.  Just use your planking of the lower platform to position it straight and against the stanchion on the fcastle bulkhead.  

Then I added the smaller section along the aft edge of the platform.  This will probably need the outside edge to be sanded because I laser cut them longer than needed.   So adjust the side that butts up against the frames.   But remember, there isnt any planking on the inboard side of the frames so it is expected to show a gap.   Just get it as even and consistent as you can.  

 

The carpenters cabin and boatswains cabin completed.

 

Note how the top of the bulkheads against the deck clamp are flush with the top of the deck clamp.    

 

fcastlecabins3.jpg

Next up will be the sail room.  But that needs to be built a different way because of the louvered walls for ventilation. 

 

Chuck

 

 

 

Posted

What a pleasure it must be to be able to design and laser cut your own custom cabin partitions. You may not like kitchen sinking but I guarantee yours is the only model with the correct three nail pattern on the cabin planking.

Would you like to borrow Gus, our office cat, to take care of your rat problem?

Greg

website
Admiralty Models

moderator Echo Cross-section build
Admiralty Models Cross-section Build

Finished build
Pegasus, 1776, cross-section

Current build
Speedwell, 1752

Posted
8 minutes ago, dvm27 said:

You may not like kitchen sinking but I guarantee yours is the only model with the correct three nail pattern on the cabin planking.

And nobody will ever see that detail once the deck beams and deck planking are completed.
 

Too funny Greg.  It actually takes a lot longer to design and draft these partitions than it does to build them.  Once they are actually laser cut,  it takes no time at all to clean them up and  install them.  
 

If only I could find someone else to do that front end work for me.

 

The sail room partitions wont be fun to design I can tell you that.  

Posted

As always, I have no words.  Truly exceptional work!  She is turning out to be a model that is worthy of display in the Smithsonian.  

Kenny

Current Builds:   HMS Winchelsea   MS US Frigate Confederacy

On Hold: Continental Frigate Raleigh 1777

Completed Builds: MS 18th Century Longboat   Dinghy - Midwest Kit    H.M.S Triton Cross Section 1/48   Chesapeake Bay Flattie - Midwest Kit

Future Builds: MS English Pinnace;  OcCre Endurance;  Revenue Cutter Cheerful

 

 

 

Posted

Thank you guys...

 

I took a crack at the sailroom.

 

First I had to make the posts for the partitions.

 

There are thin laser cut strips that need to be glued to the sides of some 3/32" x 3/32" strips.   It might be hard to see but the laser cut strips are wider than needed.   You have to line up the open side with the edge of the 3/32" strip.  Let the other side hang over.   The upright on the left shows this.  Once the glue dries, you can sand that overhang down flush with the 3/32" strip.  This will leave rows of slanted slots for the louvers.   They should be open on both sides after sanding off the overhang.   There is also a long slot down the front edge that is created.  This is for the planked bottom of each partition.  

 

It is all shown on the plans.   The corner post gets two of these laser cut strips with the notches.  Just be careful when you glue them on so they are facing the right direction and the louvers will be able to slip into the slots easily.

 

sailroom.jpg

Next I added the laser cut planked bottoms.  This essentially makes a nice two-sided partition.  The planking will fit into those long notches on the posts.  It is probably easier to see them in the photo below.  Keep a nice 90 degree corner with both sides.

 

sailroom1.jpg

Then its time to fit all of the louvers...for ventilation.

 

They are 3/32" x 1/64" strips.  Just cut them to length and start adding them.  Eight on each panel.

 

sailroom2.jpg

To finish off the sailroom..I made the door.  This is in two layers like all of the other bulkheads.   I made the door up and added the hinges and door handles.  Then I glued it to the louvered section of the sailroom.

 

Like this.

 

sailroom3.jpg

 

Now I could easily position the entire sailroom...hopefully.  It should line up and fit onto the 3/32" post already on the boatswains cabin.     And yes...we can finally glue the riding bitts into position permanently.

 

sailroom4.jpg

This pretty much finishes the cabins at the bow.   I was originally going to add a sail rack in the sailroom.  But after a lot of thought I realized it would never be seen.  The sailroom is pretty much covered up entirely by the deck planking and the deck beams.

 

In this photo I have fitted the deck beams as a test.  There will be several more between these larger deck beams too.   There are thin 3/32" deck beams...sometimes 3 or 4 between each of these larger deck beams.  They will obscure so much of the lower deck items.  But hopefully you will get a glimpse of some of this stuff as it is quite a bit of work to build it all.

 

sailroom5.jpg

 

The contemporary model with its many deck beams..

 

speedcont.jpg

 

 

Posted

One beautiful creation, do you plan on future production or are you going to keep the production to just this first batch. Yes I would love to build one but money is an issue, so for now I will just have to be satisfied with following along with your build log. Keep up the fantastic work. Thank you.

Cheers, Guy
The Learner
Current Member NRG,SMA

 

Current Build: HMS Triton 1:48 on line

 

 

 

Posted

Thank you…i will continue making more.  I have no plans to limit production.  In fact I just listed two more sets of the first two chapters.  More will follow as time and wood supply permits.

Posted

Just a quick update.  It might not look like a lot of work was done since my last post but you would be surprised how involved the deck beams can be.

 

With the cabins on the fore lower platform completed,  you can start adding deck beams above them.  No reason to wait until everything is built below deck to do so.  In fact, waiting to do it all at one time wont be very enjoyable.  Doing it this way breaks up the task a bit.

 

This kit will be very simplified compared to the books.  Because we will be planking the gun deck in the "classic" contemporary model style,  there is absolutely no need to make and add the hanging and lodging knees.   In fact, this would up the difficulty factor by about ten.   So we will just be adding the deck beams with all of the carlings and ledges.  You can however follow the Seawatch books and scratch build the knees should you really want the total experience.

 

 

The photo below has a lot going on that was completed.

 

gundeckbeams3.jpg

First, The first four deck beams were glued into position...

 

Then the carlings were added between them as shown on the plans.  The carling are cut to length using 3/16 x 5/32 strips.   

 

Lastly you may notice that the after most beams have a column under them at the center.   These are just 1/8" x 1/8" strips cut to length.  The corners are chamfered as shown on the plans.

 

With the first four beams added you can now add the ledges.   These are the thinner "partial beams" that extend from the carlings to the deck clamp.  They are laser cut for you with a special "leg" on the outboard ends.   This raises each ledge to the perfect height so it will be flush with the top of the gun deck beams.  So when you are cleaning the char off these...DONT sand the bottom or even the end with this "leg" on it.  Otherwise you wont have level ledges with your beams.    Hope that makes sense.

 

Now in that same photo above you can see the first few ledges (cleaned of laser char...no need to clean the bottom at all actually) resting in position.  All you have to do is cut the end that sits against the carling and glue it on position.

 

NOTE:  Now yes indeed...all of the carlings should be notched in the deck beams.   All of the ledges should be notched into the carlings.  But you know what...I am not going to do that.  And you dont have to either.  It simplifies things so much this way and those many mortices and notches are not so easy to make.  They will also mostly be completely covered up.   So you can decide.

 

 

Now this may all seem simple enough.  But finding the exact locations for these beams, carlings and ledges is super important.  Time and care must be taken to get their location correct....otherwise you will end up with hatches in the wrong  position and mast holes too!!  It could get ugly.

 

So use the plans.   If you have a second set printed.  Go ahead and cut them up.  You can see strategically placed cut outs on the template that allowed me to mark the locations of the carlings on the beams....and the ledges on the carlings.   This template also helped me position the deck beams properly which is the very first thing you need to do.  Finding you center line on those deck beams after they installed is also a huge help.  Gluing the parts in is easy enough...but the marking, measuring and planning takes time and patience.

gundeckbeams2.jpg

 

Then its just a matter of cutting all of those ledges to length and gluing them in position.   There are a lot of them.  I believe 86 in total.   Note that these would also be down the center between the carlings and hatches also.  But once again they will be entirely covered up and its just a repetitive exercise that nobody will ever see.

 

gundeckbeams4.jpg

To show you how the knees and other details like the ledges wont be seen...here is a look at this area with the deck planking cut and placed on the model as a test.  This shows what will be very close to the final appearance using the "classic contemporary model appearance".   But everyone can always deviate from that should they want to.

 

gundeckbeams5.jpg

 

 

Posted

If I see your new kit and some frome CAF and other manufacturers I asked myself why I started scratch building.

Really wonderful with a lot of innovative ideas.

Regards Christian

 

Current build: HM Cutter Alert, 1777; HM Sloop Fly, 1776 - 1/36

On the drawing board: English Ship Sloops Fly, 1776, Comet, 1783 and Aetna, 1776; Naval Cutter Alert, 1777

Paused: HMS Triton, 1771 - 1/48

"Have no fear of perfection - you'll never reach it." Salvador Dali

Posted

Wonderful - simply stunning.

If, now I have retired, I take up international burglary for a pastime, your house (and those fellows Siggi and Archjofo in Germany and Giampieroricci in Italy to name a few) is one I plan to visit. Would you be very kind and send me your address and a list of any days you will be away on holiday?

Many thanks

Fred

Posted

Thank you for saying...

 

I am trying to set aside time regularly to make a little progress.

 

Continuing with the center line fittings below deck, the WELL was next up.   This is a relatively simple structure.  The four sides are laser cut and etched.  You need to do just a few things before you glue up the four sides.  

 

First...make sure the fore and aft sides sit nicely on the keel.  Once you adjust them as needed,  you can cut the four upright columns to length.   How do you determine the length of these.  The two aft columns are shorter.  These are simply cut to fit under the next deck beam.  No  big deal.   The two columns on the fore side of the well are different and taller.   These two columns are cut so the tops are flush with the TOP of the gun deck beams or carlings.

You will have an opportunity to sand these shorter so dont over sand them initially.

well.jpg

Assembling the well is straight forward after you glue the columns to the port starboard sides of the well ahead of time as shown above.   You can also use some scrap tiny strips of wood to make the toggle handles for the access door.  Then just glue them on.   They are clearly shown on the plans.

 

well1.jpg

With the four sides glued up and square...test it on your model.   After any minor tweaks you can glue it position permanently.

 

well2.jpg

 

Then the next few gun deck beams, carlings and ledges were taken care of.   Eventually you will get to the beams where the capstan step needs to be built along the center line.  So you will need to stop and assemble the capstan step.   I glued those appropriate deck beams in position so I had a reference point to test fit the step periodically.  The step is also laser cut for you and has a recessed circle in the center.   This will accept the heel of the capstan drum...eventually.

 

The step is bolted to two columns that are set on top of  keel.   These two columns are 1/8" x 1/8" strips just like the other support columns under the beams.   Hopefully you havent forgotten to add any up until now.   They are all shown on the plans.  

 

You must cut the two columns to fit under their respective gun deck beams.   Now you have to determine where along those beams the capstan step will be placed.   You can use the plans of course but it is doubtful it will match your model perfectly.  Mine didnt.   So just understand that the capstan step is slightly higher the lower aft platform and it is level.   Because you know this you can mark the columns for the height of the capstan step with the columns "snug" fit temporarily in position.

 

When I was comfortable that I had the proper height worked out, I was ready to glue it in position.  But first I had to add the simulated bolts on the capstan step.   I used 25 lb black fishing line to simulate these.  And yes the photo shows the step upside down so you can see the hole for the drum.   But rest assured it will be glued in position right-side up!!

 

capstanstep.jpg

The capstan step in position...and the carlings added afterwards.

 

capstanstep1.jpg

And some other views...of the gun deck up to this point with the ledges completed.

 

capstanstep2.jpg

 

capstanstep4.jpg

capstanstep3.jpg

Almost to the other side of the gun deck.  But next up are all of the cabins on the aft lower platform.   Onward and upward as they say!!

 

 

 

Posted

That looks sooooooo nice. 

Rusty

"So Long For Now" B) 

 

Current Builds: Speedwell

 

 

Completed Build Logs:  HMS Winchelsea 1/48   Duchess of Kingston USF Confederacy , US Brig Syren , Triton Cross Section , Bomb Vessel Cross SectionCutter CheerfulQueen Anne Barge, Medway Longboat

 

Completed Build Gallery: Brig Syren , 1870 Mississippi Riverboat , 1949 Chris-Craft 19' Runabout

 

Join the conversation

You can post now and register later. If you have an account, sign in now to post with your account.

Guest
Reply to this topic...

×   Pasted as rich text.   Paste as plain text instead

  Only 75 emoji are allowed.

×   Your link has been automatically embedded.   Display as a link instead

×   Your previous content has been restored.   Clear editor

×   You cannot paste images directly. Upload or insert images from URL.

  • Recently Browsing   0 members

    • No registered users viewing this page.
×
×
  • Create New...